Subsea Hydrogen Pipeline FEED for Spain-France Corridor
Wood delivers FEED for the BarMar subsea hydrogen pipeline between Barcelona and Marseille for Enagás, NaTran and Teréga, designed for 100% hydrogen service.
www.woodplc.com

Wood has been awarded a front-end engineering design (FEED) contract by the BarMar consortium, formed by the Spanish and French transmission system operators (TSOs) Enagás, NaTran and Teréga, for a subsea pipeline that will carry green hydrogen between Spain and France. The project concerns large-scale hydrogen transport infrastructure serving industrial decarbonisation in Europe.
Partners and Roles
The three TSOs form the BarMar consortium and act as project owners, while Wood provides engineering for the offshore pipeline and associated compression facilities. Wood has been involved since the early conceptual stages in 2022, including pre-FEED engineering for the offshore pipeline and compression facilities, as well as technical support for offshore corridor reconnaissance.
Cross-Border Hydrogen Transport Challenge
BarMar is set to become Europe's first major cross-border subsea corridor designed specifically for green hydrogen, linking Barcelona and Marseille. It forms the offshore section of H2med, an EU Project of Common Interest connecting hydrogen production hubs on the Iberian Peninsula with demand centres in Central Europe. The pipeline is expected to transport up to two million tonnes of green hydrogen per year, supporting an integrated European hydrogen market and the decarbonisation of hard-to-abate industries.
Engineering Scope of the FEED
Wood will deliver the FEED for the approximately 380 km offshore pipeline and the associated compression facilities, both purpose-designed for 100% hydrogen service. The work draws on specialist capabilities in subsea pipeline design, route engineering, microtunnelling and hydrogen infrastructure. Designing for pure hydrogen requires attention to material behaviour such as hydrogen embrittlement of pipeline steels, as well as compression adapted to the low density of the gas.
Project Organisation and Schedule
The work will be led by teams in Spain and the United Kingdom, supported by specialists from Wood's global engineering network. Around 50 Wood employees will support the project, which is expected to run until April 2028.
"BarMar is a pioneering project that requires specialist engineering to safely transport green hydrogen at scale beneath the Mediterranean," said Ellis Renforth, Regional President for UK & Europe at Wood. "Our involvement since the early conceptual stages in 2022 gives us a detailed understanding of the project's technical challenges as we prepare to successfully deliver the FEED phase."